01
ingest.order
✓ SUCCEEDED
0.8 s
Plant Orchestrator · Pulled the work packages for car 07 from MES and PLM: aluminium extrusion shell, EN 15085 weld class per joint, control-plan geometry tolerances, bogie torque specifications, livery recipe and cure window, fit-out and marriage sequence. Locked the approved control-plan envelope for the shift.
-
02
takt.sequence
✓ SUCCEEDED
41 s
Line-and-Logistics · Sequenced the shift against live readiness: booth 2 cure window, bogie B-14 readiness, brake-test slot at 13:40, AMR fleet state and kit inventory. The plan moves car 07 marriage behind car 06 to keep the cure window and the test slot.
-
03
twin.simulate
✓ SUCCEEDED
58 s
Train Twin · Simulated 18 candidate weld sequences for the roof-to-sidewall joints on the as-built twin and ranked them on predicted distortion, door-aperture geometry and heat input. Sequence #6 keeps the aperture inside tolerance with 2% less heat input than the standing sequence.
-
04
weld.sequence
✓ SUCCEEDED
3 m 12 s
Weld-and-Structure · Recommended sequence #6 and the matching clamping plan to the shell line. Seam vision and laser-tracker geometry confirmed the roof-to-sidewall joints inside the control-plan tolerance on the first four seams.
-
05
approve.human
◆ APPROVAL
52 s
Plant Orchestrator · Sequence #6 lowers heat input on the roof joints 2% below the standing weld procedure. Heat-input changes stay with a named engineer, so the step was held for the shift weld engineer and approved at 06:12:44 with the twin evidence attached.
-
06
bogie.torque
✓ SUCCEEDED
continuous
Bogie-and-Running-Gear · Press-fit curves and torque traces on bogie B-14 read at the station. Two traction-motor mounting traces fell outside the expected profile and were routed to rework before brake test; the remaining safety-critical joints verified to spec.
-
07
coat.cure
✓ SUCCEEDED
continuous
Coat-and-Livery · Booth 2 humidity and temperature, film thickness and flash time watched through the livery pass. One masking misalignment on the door band flagged by booth vision before the second coat; the cure window held and handed to the sequence as a hard constraint.
-
08
marry.align
✓ SUCCEEDED
2 m 05 s
Marry-and-Couple · Carbody and bogie scans compared against target interface geometry before the lift. Fit-out readiness confirmed by Fitout-and-Interior for doors and glazing. Marriage guided inside tolerance; coupler and gangway checks verified and written to the twin.
-
09
inspect.fuse
✓ SUCCEEDED
continuous
Quality-and-Anomaly · Weld and coating vision, in-line metrology, torque, wiring continuity and brake-test results fused at the edge across the car. Every finding localised to station, work package and shift, with the two torque reworks and the masking flag already closed.
-
10
car.release
✓ SUCCEEDED
1 m 30 s
Conformance · Car 07 released: genealogy written (weld records per joint, geometry scans, torque traces, coating recipe and cure record, fit-out checks, marriage interface, approvals, test results) and dispositioned against the control plan and IRIS / ISO/TS 22163 criteria with cited evidence for the quality engineer's sign-off.